The R200 Billion Factory

A01

Envelope and split

GSX:SRD-005:A01 · Model assumption · Version 1.0

Machine-readable statement

R225 billion in constant 2026 rand is allocated across the programme. R96 billion, 43 percent, goes directly into production plants. The rest is power, water, logistics, parks, supplier finance, skills, worker housing and a R15 billion contingency.

Sensitivity: moderate. Provenance: Manuscript Part I.